Project Planning; Progress Reporting; Primavera P6; Project Control; Project Coordinating

Senior Planner, DPS Limited, Nuclear new build

START Date
Experience Hours (Planning & Scheduling)
2150
Experience Hours (Cost Management)
300
Experience Hours (Forensic Analysis)
0
  • Leading project scoping and planning activities within the Licensing, Management System, Power Station Design and Business Development programmes
  • Interfacing with the EPC contract partners; including setting schedule expectations, reviewing contractor schedules and integration of contractor schedules into the client's wider programme
  • Introducing best practice methodology in scope definition and schedule development including standardisation of Work Breakdown Structures (WBS), WBS dictionaries and Basis of Schedule documents
  • Conducting Schedule Integration Worksh

Construction Progress Engineer, Hyundai Heavy Industries, Crude Export Facilities. EPIC Project, Kuwait National Petroleum Company (K.S.C.) Clean Fuels Project (CFP), Kuwait Oil Company

START Date
Experience Hours (Planning & Scheduling)
33800
Experience Hours (Cost Management)
6000
Experience Hours (Forensic Analysis)
2000

• Monitor and documented construction progress. Developed progress measurement system (PMS) for monitoring construction progress. Working experience with tools e.g.