Project Planning Processing to successfully plan. BPCS Business planning & control system managements. • • Project Management involving Physical

Lead Planning Engineer, Black & Veatch, Europe Larger Combine Heat and Power Project

START Date
END Date
Experience Hours (Planning & Scheduling)
5500
Experience Hours (Cost Management)
5000
Experience Hours (Forensic Analysis)
5500

Conoco Phllips Oil & Gas Immingham ICHP2  EPC Project of 412 Mega Watt 

u  Managing EPC Program of 8,529 activities of construction, engineering and procurement in Primavera. Project contains 17 sub-projects and 9 sub-contractor.

u  Integration of sub-contractor projects into main project.

Lead Planning Engineer, Black & Veatch, Europe Larger Combine Heat and Power Project

START Date
END Date
Experience Hours (Planning & Scheduling)
5500
Experience Hours (Cost Management)
5000
Experience Hours (Forensic Analysis)
5500

Conoco Phllips Oil & Gas Immingham ICHP2  EPC Project of 412 Mega Watt 

u  Managing EPC Program of 8,529 activities of construction, engineering and procurement in Primavera. Project contains 17 sub-projects and 9 sub-contractor.

u  Integration of sub-contractor projects into main project.

chief operation officer, Al Meraikhi General Contracting, alfaraa general Co.L.L.C, bin ladin group, CCC (Consolidated Contractors Company), Modern Executive Systems Contracting L.L.C (Dubai), Airport, hotel, Infrastructure, luxury villas, Malls, residen

START Date

 

Application for position:

Dear Sirs,

I would like to apply the post of   

Senior Enginering Managment

PLANNING, BUDGETING, RMP, PMI, PMP & BPCS



Kindly Find attached herewith my Resume for your kind consideration to the above post and hopes to meet your satisfaction.