Project Controls Specialist

PROJECT CONTROLS LEAD, Saudi Aramco, Project Portfolio

START Date
END Date
Experience Hours (Planning & Scheduling)
4000
Experience Hours (Cost Management)
1000
Experience Hours (Forensic Analysis)
1000

PROJECT CONTROLS LEAD

 

SAUDI ARAMCO, SAUDI ARABIA

 

• Implemented project milestones, schedules and cost controls throughout the life span of multiple projects.

• Schedule development, reviews and identifying schedule risk and deviations/variance from project plans.

• Developed business/operating plans, accountability reports, project scope of works, and technical presentations.

Project Controls Manager, CLP Power, New CCGT Project

START Date
Experience Hours (Planning & Scheduling)
4000
Experience Hours (Cost Management)
2000
Experience Hours (Forensic Analysis)
500

PROJECT CONTROLS MANAGER

 

CLP POWER, BLACK POINT POWER STATION, HONG KONG

 

Project Controls Manager for Owner’s Team, overseeing two key power upgrading projects as part of Hong Kong’s commitment to cleaner and more economic power:

 

Senior Cost Engineer, Senior Planner, Project Controls Manager, Project Controls Management Services Pty Ltd, Buildings, Industrial, Oil & Gas, Petro Chem, Pharmaceutical, PIPELINES, Rails, Refinery

START Date

Had over 20 years in the construction industry of combined working experience in the field of oil & gas refinery, pharmaceutical plant, waste water treatment & recycle water treatment plant, high rise building, module assembly, on-shore pipeline installation, power plant, industrial plant  and heavy civil infrastructure.