Project Controls Planning and Project Delivery Support

Project Controls Specialist, Foster-Wheelr/WorleyParsons, Singapore Parallel Train (SPT)

START Date
END Date


Client: ExxonMobil Chemicals/Refinery

Managing subcontractor’s execution for project completion
Current subcontractor: Mechanical Piperacks – Fabrication, Logistics, & Construction

•Assisted in the development and maintenance of integrated schedules which included, detail design, procurement, construction and commissioning stages.
•Use project cost estimates to resource load project schedules and gain alignment with estimated scope of work.
•Weekly travels to the fabrication yard to oversee and monitor progress and help in organizing logistics for timely del