PLANNING ENGINEER, GEC Qatar, Samrya Hotel Suites (B3+G+M+44)

START Date
  •  Preparation of Clause 14 Baseline Program for project at the tendering stage as per the scope of work in Primavera 6.
  • Complete resource planning including labour & non labour (Machinery) as per project scope using productivity norms.
  • Coordinate between client & consultants for various issues at site regarding work progress & for issues impacting activities on the critical path.
  •  Review & analysis of Contract documents for each Constr

EPC Senior Planner, Nurol LLC, Villas, School

START Date

v  Qualified Planning Engineer with around 6 years of experience in Project Management, Project Proposal, Construction Management, Resource Planning, Business Development and Cost Control with organization of repute in India and UAE.

Currently Associated with Nurol LLC, Abu Dhabi, UAE

Assistant Manager - Project Management, CBRE South Asia Pvt. Ltd., Residential project comprising of Apartments (27 towers of Basement+Stilt+8), Club houses, Luxury Villas (151 No's)

START Date

Project Planning – Preparation of Master construction schedule, Periodical progress tracking and reporting, resource planning and Cash flow projections. Reporting – Sending out Daily progress reports, Fortnightly reports, Monthly reports (Management Information Reports), Weekly quality reports, Weekly safety reports and Photo reports.

Assistant Manager - Project Management, CBRE South Asia Pvt. Ltd., Residential project comprising of Apartments (27 towers of Basement+Stilt+8), Club houses, Luxury Villas (151 No's)

START Date

Project Planning – Preparation of Master construction schedule, Periodical progress tracking and reporting, resource planning and Cash flow projections.
Reporting – Sending out Daily progress reports, Fortnightly reports, Monthly reports (Management Information Reports), Weekly quality reports, Weekly safety reports and Photo reports.
Project documentation: Maintaining Delay record, Site Log, Hindrance register, Site order Book, Drawing register, RFI tracker, Site instruction tracker, NCR tracker, MOM tracker
Meetings: Conducting Design review meetings, Progress review meetings, Escalation

Assistant Manager - Project Management, CBRE South Asia Pvt. Ltd., Residential project comprising of Apartments (27 towers of Basement+Stilt+8), Club houses, Luxury Villas (151 No's)

START Date

Project Planning – Preparation of Master construction schedule, Periodical progress tracking and reporting, resource planning and Cash flow projections.

Reporting – Sending out Daily progress reports, Fortnightly reports, Monthly reports (Management Information Reports), Weekly quality reports, Weekly safety reports and Photo reports.

Project documentation: Maintaining Delay record, Site Log, Hindrance register, Site order Book, Drawing register, RFI tracker, Site instruction tracker, NCR tracker, MOM tracker.

Assistant Manager - Project Management, CBRE South Asia Pvt. Ltd., Residential project comprising of Apartments (27 towers of Basement+Stilt+8), Club houses, Luxury Villas (151 No's)

START Date

Project Planning – Preparation of Master construction schedule, Periodical progress tracking and reporting, resource planning and Cash flow projections.

Reporting – Sending out Daily progress reports, Fortnightly reports, Monthly reports (Management Information Reports), Weekly quality reports, Weekly safety reports and Photo reports.

Project documentation: Maintaining Delay record, Site Log, Hindrance register, Site order Book, Drawing register, RFI tracker, Site instruction tracker, NCR tracker, MOM tracker.