Progress reporting

Engineer Planner, Sunway Construction Sdn Bhd, Railway Construction, University Tower & Shopping Mall

START Date

 

MyRapid Transit (MRT) (Semanthan to Damansara) – (RM 1, 400, 000, 000.00)

 -assist planning manager to develop master work programme.

 -monthly update & fortlnightly progress report.

 -update & develop 2 weeks & 2 month look ahead for forecasting purpose.

 

 Sunway University – New University Building – (RM 325,000,000.00)

 -develop master work programme.

 -prepare & furnish planning sheet on programming purpose.

Construction Project Planner / Senior Planner, Yildizlar Group, Company Headquarter

A
Alper YIGIT 👤 Member for 19 years 4 months
START Date

 

I was invited by one of my ex-managers, who was appointed to set an ‘international projects department’ within the company, in order to take part in the process of structuring the department. My tasks were (1) to constitute the required planning and cost control management structure for a project management culture with a real time predictable, controllable, and reportable project management understanding and (2) to systematically employ this culture to the awarded projects. 

Planning Engineer, ALCON, Office Accommodation Building

M
Mathew E. 👤 Member for 13 years 7 months
START Date

Planning Engineer

Job Description:

-          Preparation of project schedule using primavera P6 v7.

-          Preparing and keeping updated Two Week Look-Ahead Bar Charts and Plans.

-          Preparing and keeping updated Progress S-Curves.

Planning Engineer, SNC Lavalin Thermal Power, Iraq Fast Track Project 4x125 MW

START Date
END Date

 

  • Programmed of Work , Progress “S” Curve,  Manpower histogram (By trade).

·          Monitoring actual of progress comparing with BOQ 

·          Maintain and update Project schedule

·          Work variation and forecast volume 

PLANNING ENGINEER, Chevron , Gorgon LNG Downstream Project

START Date
END Date

 

The Greater Gorgon Area is located 200km offshore of the northwest coast of Western Australia and contains in excess of 40 trillion cubic feet of recoverable natural gas.

·         16.5m Manhours (EPC)

·         200K Tonnes overall

·         97K Tonnes of structure steel