Primavera Planning & Scheduling

Site Planner, Shin Eversendai Engineering, 1 X 1000 MW Coal Fired Supercritical Boiler

START Date

 

Project: 1 X 1000 MW Coal fired Supercritical Boiler

• Implementing and supervision of mill, pulverizer and boiler installation for Power Plants of capacity 1000 MW.

• To ensure planning, scheduling & timely execution of all Mechanical Erection & Commissioning related work of 1 X 1000 MW Power Project at site.

• Good knowledge of boiler components, including pressure parts, pre assembly, structure erection of Heavy equipment with specific experience of preparation of lifting plan.

Site Planner, Nexen Petroleum UK Ltd, Golden Eagle

START Date
END Date

Based on site at Jebel Ali, Dubai, UAE on the construction and commissioning of 2 topsides. Responsibilities include maintenance of the construction plans, development and maintenance of the commissioning plans and reports using Primavera P6.  

Project Support Officer, Scottish Power, Blackstuff

START Date
END Date

Working for Innovation Business Vision which is a project management/project control consultancy. The following project was undertaken on their behalf.

Working as a planning consultant at Scottish Power. Tasks included creating a project schedule and associated progress measurement/ reporting structures. Preparing detailed cost/budget reports and projections.

Commissioning Planner, AIOC / BP, ACG Topsides Project

START Date
END Date

Based in Baku and responsible for the development and maintenance of the topsides commissioning plans for the West Azeri, East Azeri & DUQ platforms (ACG Project Caspian Sea). The platforms of approximately 15,000Te contained process, drilling and accommodation facilities. Being a client role, tasks included co-ordinating contractor planning efforts, along with reporting to site and overall project management. The commissioning team was an integrated team, and as such the role included hands on ownership of the plan.

Senior Planner, Woodside Energy Ltd, Angel

START Date
END Date

Based on site in Malaysia responsibilities included reviewing the contractor’s construction plan and reports and the development and maintenance of topsides commissioning plan. Tasks included weekly and monthly reporting to site team/head office and overall project management. Development and maintaining the plans in Primavera P5, developing reports for the weekly reporting on progress, ITRs/FTRs and CTP completions, man hours/man power and productivity, Also provide the project management team with ad hoc plans and reports.