Engineering Planner, GE Oil & Gas, Subsea Trees

START Date

Summary of my responsibilities are:

 

  • Construct and manage detailed planning schedules, utilizing Primavera P6 software, that represent activities required to successfully deliver key project / scheme milestones;
  • Developplans to sufficient detail to ensure effective control of all project deliverables.
  • Identifycritical activities and continuously monitor and report to project manager
  • Generateproject reports that reflect the actual project status both with respect to time and performance
  • Ensure planning and reporting require

PLANNING ENGINEER, SAIPEM NIGERIA LIMITED-(ENI GROUP), East Area Projects-EPC4A offshore Wellhead Retrofit and Revamp Project-Engineering

START Date
END Date
Experience Hours (Planning & Scheduling)
3800
Experience Hours (Cost Management)
100
  • Preparation of Project Schedule for all disciplines like Civil, Mechanical, Electrical and Instrumentation Activities with performed task & milestones.  
  • Plan and extract weekly / monthly look a head schedules updates & analysis.
  • Prepares various monthly, other periodic and adhoc activity reports to keep management advised of status, progress, financial commitments and major areas of concern pertaining to on-going projects.

Project Planner, Network Rail, Civils East Anglia Upgrades

START Date
END Date

 Project Planner on Civils East Anglia Framework Contract for Network Rail

 

  • Responsible for salvaging a project work bank of around 100 live civil engineering projects using P3e.
  • Creating cost loaded plans with complete logical dependencies, baselines for monitoring/evaluation, complete WBS coding structure, critical paths and physical progress measures.
  • Producing recovery programs to ensure project critical milestones are met on time.
  • Creating and managing a monthl

Project Planner, JP Morgan, West Coast Modernization Route

START Date
END Date

Project Planner on West Coast project for Network Rail

 

  • Planning the commissioning stages of the West Coast and Axle Counter projects using P3.
  • Axle Counter project had extended end dates which were resolved by innovative use of possessions and access along with reallocation of resource/contractor teams to maximise performance and ensure no opportunities slipped by.
  • Generated weekly progress reports including milesto

TASS Data Technician, Network Rail, West Coast Modernization Route

START Date
END Date

TASS Data Technician for Network Rail producing completion certificates and updating strategic programme in P3 for the West Coast Mainline project.  Also assisted in carrying out gauge clearance analysis for the Pendolina KE8 train.

Project Planner, ABB Ltd, 1.Replacement of Wakefield B 132 kV GIS – 15 Million GBP [ Client CE Electric ], 2.Walpole 132 kV GIS, SGT5 and Centrica Bas Bar Extension – 35 Million GBP [ Client National Grid]

START Date

 

Project Planner/Mechanical Engineer

(17 years experience)

 

  • Prepared, maintained and monitored project plans/schedules.
  • Significant skill on Planning Tools [ Primavera P3 version 3.1,Microsoft Project]
  • I got training on Planning Tools P6 and currently working on P6.
  • Performed critical path analyses, earned value analyses, resource leveling.
  • Involved with site planning in terms of programming and progress monitoring.
  • Worked / lia

PLANNING ENGINEER, Square General Contracting Co. (L.L.C.), Dubai (UAE), Florence) at Jumeirah Village, Siena, Tuscan Residences (Arrezo

START Date
END Date
Experience Hours (Planning & Scheduling)
3000
Experience Hours (Forensic Analysis)
1500

Job Responsibilities: