possession planning

Senior Consultant, Jacobs, Thameslink KO2 London Bridge, Crossrail Intermediate Shafts, Bank Station Upgrade

P
Phil Butler 👤 Member for 20 years 9 months
START Date
END Date
Experience Hours (Planning & Scheduling)
3900
Experience Hours (Cost Management)
200
Experience Hours (Forensic Analysis)
200

Providing planning advice and developing programmes on a number of rail project

Senior Program Manager, Sydney Trains (Transport for NSW), Various Projects

H
Herman Louw 👤 Member for 19 years 3 months
START Date
END Date
Experience Hours (Planning & Scheduling)
3000
Experience Hours (Cost Management)
2000
Experience Hours (Forensic Analysis)
1000
  • Lead, coordinate and manage the delivery of the Annual Work Program (AWP) within the Maintenance Directorate, focusing on achieving safe and cost effective performance, timely project deliveries and reliability objectives of the asset and business.
  • Manage possession strategy and planning to coordinate effective delivery of the AWP, external party, and major capital upgrading and development projects.

Project Planner, Xervon Palmers, Edinburgh Waverley Station Redevelopment

START Date
END Date

Initially employed as part of the National Bid Team responsible for developing Tender Programmes for various bids taking place across the UK.  Thereafter a part of the Edinburgh Waverley Station Redevelopment Project Controls Team responsible for monitoring and evaluating the earned value and productivity targets set in the client’s programmes.  Duties also included creating possession programmes for works taking place during rail track isolations and providing the Quantity Surveyors with the necessary information to assess the current/future position of the works to accurately pr

Project Controls Consultant, London Underground Limited, LUL Track Renewals programme

S
Simon Lee 👤 Member for 21 years 4 months
START Date
END Date
Experience Hours (Planning & Scheduling)
3600

Providing Project Controls advice as part of a specialist mobilisation team working with a Balfour Beatty/LUL partnership for a new 5 year NEC3 Option C track renewal and maintenance contract.  Advice and hands on assistance in setting up appropriate scope control, project coding, change control and cost and resource loaded programmes, all to enable effective planning and monitoring of progress and timely issues identification.