platform

Planning Engineer, Mustang Engineering, Alternative Bridge Landing Module (ABLM) on the North Rankin A (NRA) platform

START Date
END Date

Prepared level-3 and level-4 (deliverables level) plan by P6 c/w histograms aligned with CTRs and SDS (Supplier Documents Schedule); monitored progress; and interfaced with Transfield Worley as construction contractor

Project Control Engineer, Technip, Sisi Nubi Field Development– Phase 1, Onshore Facilities for Gendalo Field Development, Sadewa-Z WHP and Pipelines, Onshore Facilities for Gehem Field Development (Indonesia)

START Date
END Date

Established the project setup (project coordination plan, project quality plan, schedule, and budget incl. CTR – Cost, Time & Resources); monitored and rectified the implementation (recovery plan, daily / weekly / monthly report, MOM, supervising document controllers); compiled technical documents, such as Scope of Work and Basis of Design; and handled commercial matters of the project (cost report, change order, level-4 cost estimate, and invoicing)