Regional Manager, Ataman Libya Construction Co., 200 Villa Project in Tobruq-Libya

START Date
END Date

REGIONAL MANAGER (SITE MANAGER) : I was responsible for all business development activities in the territorry of Libya for superstructures such as residence, hotels, office buildings,etc. We were awarded by a $43m - 200 Villa Project in Tobruq city, Libya.

Project Controls Supervisor, Carter Brothers, CDC

START Date

 

 

  • Performs complex evaluations of existing procedures, processes, techniques, models and/or systems related to management problems or contractual issues.
  •  

     

     

     

  • Develops work breakdown structures, prepares charts, table, graphs and diagrams to assist in analyzing problems.
  •  

     

     

     

  • Assists in the preparation of management plans and reports.
  •  

     

     

    &nbsp

    Utilities Co-ordination, Buro Happold, Heathrow Terminal 2 - Multi Story Car Park and Infrastructure

    START Date

    Provision of a Project Management and Planning Services for the Heathrow Terminal Two MSCP, Structural Ramps, Highways and surrounding Infrastructure. 

     

  • John's activities include:
      • Co-ordination of overall site utility design, protection, diversion, removal and interfaces.
      • Design and management support and where necessary leadership for the Utility Design co-ordination involved with this project.
      • Undertaking Gap analysis of information received and take necessary steps to obtain missing information

    Planning and Cost Control Engineer, METIS CONSTRUCTION AND TRADE CO., Roads & Infrastructure Projects

    A
    Alper YIGIT 👤 Member for 19 years 4 months
    START Date
    END Date

    ·         Planning and Cost Control Engineer for Industrial Projects in Libya

    I prepared and monitored; Work Programs for Railroad Bridge, Dam, Pump Station, and Pipeline projects in coordination with sites. Furthermore I studied cash flow and financial standing of the projects in cooperation with the finance department and periodically reported the work to the head management of the company.

     

    Assistant to Contract Administrator, METIS CONSTRUCTION AND TRADE CO., SIRT Pump Stations

    A
    Alper YIGIT 👤 Member for 19 years 4 months
    START Date
    END Date

    Assistant to Contract Administrator

    I worked together with the contract administrator to define Actions and Strategies against the contractual problems on different issues regarding the project thus to strengthen company’s contractual position.

    Project Planning Consultant, Celikler Holding , Construction of Ayn Ziyaneh, Sidi Halife, and Bingazi Airport Roads

    A
    Alper YIGIT 👤 Member for 19 years 4 months
    START Date
    END Date

    Celikler Holding Ankara, TURKEY

    Freelance Consultant

    I prepared and submitted the Time Schedule, Resource Planning, and Cash Flow for a starting project in Libya; Construction of Ayn Ziyaneh, Sidi Halife, and Bingazi Airport Roads. I also submitted the required software packages that the company needed for its further operations regarding the Project.

    Lead planner / Planning Manager, Engineering Consultants Group (ECG), Cairo Festival City

    START Date
    • Review, upgrade, development and implementation of the project control system and integration with administrative and operational procedures of the Project.
    • Oversee and monitor contractors’ submittals of material samples, data, shop drawings and technical data.
    • Review of contractor schedules, updating and status reporting to the Director of the Committee on same.
    • Oversee documenting of design and construction budgets, cost estimates, associated financial reporting including cash flow projections.
    • Oversee the logs and tracking proposed design and construc