Planning Engineer/Scheduler, QDVC (Qatari Diar Vinci Construction), Commercial, Infrastructure, Channel Tunnel Rail Link

P
Peter Dua 👤 Member for 14 years 5 months
START Date
  • Produce a comprehensive and viable construction program in conjunction with the Project Manager and designates using Scheduling Software Primavera P6.7
  • Verify the actual progress versus scheduled progress on a daily basis alerting the Project Manger of any areas of concern regarding schedule slippage of line items & the knock-on effect to related activities.
  • Preparation of Overall Progress Monthly Report to the Client as Contractual requirements showing all progress and updates from concern departments.
  • Preparation of application of Interim Payment to includ

Assitant Techinical Officer, GTP, Various

START Date
END Date

Various

Project Description: Oil storage tanks (11) with security system, El Eulma and Oily separator center, TFT South of Algeria.

Responsibilities/Tasks:Work progress control (using earned value), scheduling and forward project, schedule analysis and monthly report preparation.

 

Project Description: Diesel power plant, Illizi.

Assistant Engineer / Document Controller, Fluor - Tripatra Consortium, Gametri Tirta Lestari Co. LTd, Flexible Program Management

START Date
END Date

1 June 2010 – Now

Fluor - Tripatra Consortium, Co. Ltd– Duri

Flexible ProgramManagementII & III

Position :   Document Control

 

 

 

Project Highlights,

 

Planning Engineer, Topaz Energy & Marine Ltd, EPCL Refinery T & I Shutdown 2011

I
Irfan Malik 👤 Member for 14 years 8 months
START Date

 

Ø  Identification and Analyzing of Scope of work

Ø  Preparation of detailed integrated Level IV Plan

Ø  Preparation of work packages for execution of jobs including the detailed method statements

Ø  Preparation of manpower deployment and equipment deployment plans

Ø  Estimate manpower, spares/material in consultation with Execution and maintenance engineers

Planning Engineer, Descon Engineering Abu Dhabi, Maintenance Shutdowns & Construction Projects

I
Irfan Malik 👤 Member for 14 years 8 months
START Date
END Date

 

Ø  Finalization of Scope of work

Ø  Preparation of detailed integrated Level IV Plan using Primavera.

Ø  Estimate manpower, spares/material in consultation with Execution and maintenance engineers

Ø  Responsible to analyze schedule status, physical progress, man-hours consumption, productivity, network logic, work sequence and three weeks and Four months look ahead plans.