Manager - Planning Engineer, MBVillar Group of Companies, Residential Community Development

START Date
END Date

 

-           Prepare project time schedule for subdivision development for low cost & middle cost housing project.

-           Supervise group of AutoCAD operators in preparing subdivision development plan and residential building plan.

-           Estimate and prepare bill of materials for residential and subdivision development.

Programme and Project Control Manager, Katanga Mining, Upgrade(Brownfield) of a Copper and Cobalt refinery to produce upwards of 150 000t of Copper and 30000tons of Cobalt. (Value is $900m).

START Date
END Date

Achieving the scheduled performance, cost, quality, health, safety and environmental requirements of the project from contract award to Operations acceptance whilst negotiating all contract changes with the EPC, Vendors and Contractors if necessary. Authorization to determine all matters affecting the implementation and operation of the contract. Initiating the formulation of project policy or recommendations for the Client in all key areas in particular planning, procurement, estimating, and constructing and contract changes.

Project Control Manager, Shell, Onshore and Offshore Facilities and major Pipelines for Oil, NAG and LNG to Port terminals

START Date
END Date

Responsible for managing the project/s Project Control department on a day to day basis. Development of timescales and associated deliverables as well as effectively managing a team of Planners/Costing engineers, technical assistants. Responsible for compilation of  Weekly and  Monthly reports on progress, cost and highlights, achievements, concerns, mitigations, Look ahead also producing Top project one pager reports for clients/Owners/Shareholders. Manage overall Costs and direct involvement in developing Level 1 to 6 Cost Breakdown structures.

Project Control Engineer / Project Control Manager, Worley Parsons Australia, Roy Hill Greenfield Iron Ore mine

START Date
END Date
Experience Hours (Planning & Scheduling)
700
Experience Hours (Cost Management)
700
Experience Hours (Forensic Analysis)
700

SUMMARY OF EXPERIENCE :( General overall experience on projects)

 

Planning Manager, Costain Civil Engineering, Thames Water AMP3

START Date
END Date

 

Responsibilities: Development of planning system for construction and design engineers to improve management and control of many projects totalling around £15 million annual turnover. Identifying areas for improvement in partnership performance and initiating change.