planning

production of project plans

Planning & Project Control Manager, Elecnor, La Raisa temporarl and Termocentro projects

START Date
END Date
Experience Hours (Planning & Scheduling)
350
Experience Hours (Cost Management)
350
Experience Hours (Forensic Analysis)
150

Key Leader responsible of developing and issuing the Project Control procedures, the Risk and Opportunity Management Plan, the Contract Master Schedule and the internal Control Budget for building four electrical substations along with their electrical interconnection by means of 230 Kv power lines (Termocentro- turnkey project). Main duties included:

PCM or Senior Planning Engineer, Eni saipem, Pemex Clean Fuel Projects

START Date
END Date
Experience Hours (Planning & Scheduling)
750
Experience Hours (Cost Management)
750
Experience Hours (Forensic Analysis)
400

Main Planner and Controller for the construction of two desulphurization units and two amine regeneration units-PEMEX Clean Fuel (ULSG) Project (EPCC contract) with a core role for the design, establishment and management of a planning and progress control system. Responsibilities include:

Assistant Manager - Pm & Planning, Millat Group of Companies, Pakistan, Millat Group Multiple Projects

START Date
END Date
Experience Hours (Planning & Scheduling)
900
Experience Hours (Cost Management)
800
Experience Hours (Forensic Analysis)
50

Assisting PM in planning, scheduling, tracking, reporting, forecasting, resource control.

Senior Planning Engineer, Al Muhaidib Contracting Comapny, Taibah Hospital Project Madnia - KSA

START Date
Experience Hours (Planning & Scheduling)
850
Experience Hours (Cost Management)
950
Experience Hours (Forensic Analysis)
150

Planning, Scheduling, Tracking, Forecasting, Reporting, Claims Handling, contract handling, technical support. 

Planner, Northumbrian Water Ltd, Northumbrian Water Projects

M
Mike Duffy 👤 Member for 14 years 10 months
START Date
END Date
Experience Hours (Planning & Scheduling)
1000
Experience Hours (Cost Management)
1000

Design and costing of water mains extensions and diversions, ordering non-stock material, control of costs, monitoring progress of schemes, preparation of final accounts and dealing with prospective developers and site agents on a day-to-day basis

Planning Engineer, Consolidated Construction Consortium Limited, DMRC IT park

START Date
END Date
Experience Hours (Planning & Scheduling)
4000
Experience Hours (Cost Management)
4000
Experience Hours (Forensic Analysis)
4000

CONSOLIDATED CONSTRUCTION CONSORTIUM LTD, NEW DELHI.
Planning Engineer
April 2008 – April 2010

Project:
DMRC IT Park (2B+G+8 storey building) at New Delhi – (US$ 15M)
Police Station Building (3B+G+10 storey building) at New Delhi – (US$ 6M)
Narayana Hospital (G+5, 4 buildings) at Jaipur – (US$ 4M)
Sarovar Hotel (G+3, 3 buildings) at Roorkee – (US$ 2M)
Dwarka Water Treatment plant (Water Treatment & Retaining Structures) at New Delhi – (US$ 7M)
Keshopur Sewerage Treatment Plant at New Delhi – (US$ 6M)
Cadbury Project (G+4, 5 buildings) at Baddi – (US$ 6M)

Responsibilities:
• R

Planning Manager, CBRE South Asia Pvt Ltd. Chennai, Aqualily Residential Development

START Date
END Date
Experience Hours (Planning & Scheduling)
7000
Experience Hours (Cost Management)
7000
Experience Hours (Forensic Analysis)
7000

CBRE SOUTH ASIA PVT LTD., (Project Management Group), CHENNAI. Manager Apr 2015 – Jun 2015 Deputy Manager Aug 2013 – Mar 2015 Assistant Manager Oct 2011 – Jul 2013 Project: Mahindra Aqualily Project (151 villas (G+1) + 22 Apartments (St+5), (B+G+7), (St+7/8) with complete Infrastructure Development) at Mahindra World City – (US$ 50M) for Mahindra Lifespace Developers Ltd. Responsibilities: • Working as Planning Manager, reporting to PMC Project Lead • Preparation of Project Master Schedule & Monitoring progress • Monitor project performance based on time cost and quality.