P6

Senior Planning & Schedule Engineer, PT. Punj Lloyd Indonesia, 2x30MW Coal Fired Power Plant, Tanjung, Tabalong – Kalimantan Selatan, Indonesia.

START Date
END Date
  1. Create, maintain and updating Master Schedule (using Primavera Version 5).
  2. Create Two Weeks Look Ahead Schedule in level 5.
  3. Review Sub-Contractor schedule and progress and ensure the progress of Sub-Contractor is correct.
  4. CPM analysis.
  5. Oversee any possible delay of work and prepare catch up plan.
  6. Studied the possibilities of delays in the work and proposed solutions to overcome these delays.
  7. Plan allocation of labor and equipment and compare with actual conditions in the site.
  8. Make a budget plan using Primavera P5

Planning Manager, ALSTOM Transport, Incheon Airport Railway Project

START Date
END Date

Incheon Airport Railroad Project, Korea



Developed Programme/Schedule:

Baseline Contract Schedule (Primavera P3)

Progress Monitoring Tools for Manufacturing & Delivery (Excel)

Progress Monitoring Tools for Installation (Excel)

Track Related Installation Programme (Excel)

Test and Commissioning Schedule (Primavera P3 & Excel)



Reporting:

Monthly Progress Report

Monthly Progress Presentation

Weekly Progress Report

Critical Path Analysis

Planner, Thales, Rail Signalling Projects

START Date
END Date
Experience Hours (Planning & Scheduling)
1000
Experience Hours (Cost Management)
500

Project Description

Numerous bids and projects relating to telecoms for the UK rail industry.

Roles and Responsibilities

Part of two-man team responsible for planning & control of all projects in southern Britain, including Earned Value reporting, tracking actual spend at detailed activity level, and resource utilisation forecasts to inform strategic manpower decisions.