Senior Planner, Mott MacDonald, Heathrow Q5

START Date
END Date
Experience Hours (Planning & Scheduling)
700
Experience Hours (Cost Management)
350
Experience Hours (Forensic Analysis)
250

Project Description

MSP services to BAA for managing 5-year programme of capital works at Heathrow Airport, UK.

 

Role & Responsibilities

Lead Planner on behalf of BAA for a number of projects within their "Portfolio of Projects" sub-programme.

Project Controls Specialist, Fluor Daniel SA, Project Turbo

START Date
END Date

Employed as lead planner reporting to Project controls manager.
Overseeing of construction contracts for civil works, under ground services, structural steelwork, field fabricated tanks and the construction of a new cooling water tower.
Review and compilation of submitted Compensation events for Project managers assessments and Early warning matters as required by the NEC.
Progress monitoring, Issuing of Early warnings to Contractors and Employer.
Contractor interfacing and scheduling of early requirements.
Conversion of work package based schedule to a systems structured han

Forensic Planner / Delay Analyst, Schofield Lothian, Multiple Clients

START Date
END Date

 

Planning Consultant Schofield Lothian  Planning consultant;• Delay analysis for civil contractor on rail signalling upgrade project in South Wales.• Kings Cross Underground Redevelopment (Phase 2)