Procurement Expeditor representative, Procurement Manager, Alliance Planner & Scheduler, NIOEC Co., Shazand Arak Refinery development Project, SARP, Esfahan Refinery Extention Unit Project, ERUP

START Date
END Date
Experience Hours (Planning & Scheduling)
2500
Experience Hours (Cost Management)
3000
Experience Hours (Forensic Analysis)
500

 

Project Title             : Shazand Arak Refinery development Project,  SARP

Project Duration      : 1 Years, 1  Months

Role                           : Procurement Expeditor

Team Size                 : 30

Assistant Engineer Gr I (Civil), National Buildings Construction Corporation Ltd., Bombay, Fourth Oil Berth Project at Butcher Island

START Date
END Date

Construction of Fourth Oil Berth Project at Butcher Island, Bombay, India,  comprising an approach bund 547m long, an approach jetty 5.9m wide & 1248m long and berthing and mooring facilities for vessels up to 1,50,000 DWT, designed by STUP INDIA Consultants and execution consultancy by Christiani & Nielson a Danish Construction Company