Field Engineering

Project Engineer, MWKellogg, Several Projects - North Africa, and US

START Date
END Date
Experience Hours (Planning & Scheduling)
6000
Experience Hours (Cost Management)
6000
Experience Hours (Forensic Analysis)
2000

M W Kellogg- Field Project Engineer

Houston, Texas

CF Industries, Inc.

UREA 4 Plant Expansion - Donaldsonville, Louisiana

Shane Fandry – CF Industries Project Engineer

 

Project Control Engineer, ACCI, Boeing, Chiyoda, Hill intl., METRO, Raytheon, USACE, Commercial, Industrial, public infrastructure, Residential

START Date
END Date
Experience Hours (Planning & Scheduling)
18000
Experience Hours (Cost Management)
8000
Experience Hours (Forensic Analysis)
8000
  • Raytheon, Chemical Weapons Disposal Incinerator, Umatilla, OR ($1.3 billion) Scheduler for the general contractor constructing a new lethal chemical agent incinerator plant. Prepared cost and resource-loaded time impact analysis schedules for project change orders. Chaired the weekly superintendent schedule review meeting and produced the weekly craft-level “look ahead” work schedule. Updated the monthly cost-loaded billing schedule needed for pay applications.
  • ACCI, Bellevue, WA As Senior Scheduler prepared schedule delay analysis and exhibits for expert witnesses.

Consultancy Project Controls Engineer, AECOM, Commercial, Highway, Industrial, Residential, Transit, tunnel and airport construction

START Date
Experience Hours (Planning & Scheduling)
18000
Experience Hours (Cost Management)
6000
Experience Hours (Forensic Analysis)
8000
  • Sound Transit Central Link Light Rail, Beacon Hill Tunnel, Seattle, WA ($310 million) Served as Scheduler on the construction of a twin bore 21’ diameter, one-mile long light rail tunnel, associated trackwork and two transit stations. Reviewed and approved contractor CPM Schedule baseline and update submittals for completeness, accuracy and contract compliance. Prepared critical construction progress trend and status reports, responded to contractor delay claims, prepared Time Impact Analysis and as-built schedules. Prepared cost estimates for change orders.

Project Engineer / Field Controls Manager, JGC Corporation, Bab Field Production Facilities Expansion Project, Abu Dhabi U.A.E. (350 MBOPD)

N
Nazir Ahmad 👤 Member for 19 years 2 months
START Date
END Date
  1. Coordination with Engineering disciplines & Procurement during engineering phase in Yokohama Japan as Project Engineer
  2. Coordinate with project team members to get required information for cost estimate
  3. Coordination with Vendor regarding engineering & vendor data for finalization of Engineering & Procurement issues
  4. Project planning, monitoring & control to meet the EPC project requirement
  5. Preparation of Project Weekly/Monthly Progress reports for client
  6. Work in collaborative relationships with client in the planning &am