Project Planner, Cairnhill Structures Scotland, Pater-Costain-AWE Mensa Project, Reading

M
Michael MAO 👤 Member for 7 years 3 months
START Date
END Date
Experience Hours (Planning & Scheduling)
500
Experience Hours (Cost Management)
150
Experience Hours (Forensic Analysis)
300
  1. Prepared resource loaded Programmes for complex technical projects using MSP and P6
  2. Effectively administered and discharged NEC Contract Programme requirements
  3. Secured Extension of Time claims by demonstrating acceptable excusable delay events in Project Programmes
  4. I improved the quality of Project Programmes by carrying out integrity and quality assessment of Programmes in line with industry standard folling DCMA14
  5. Ensured that project progress updates are submitted on time to clients by providing Site Managers and Proj

Lead/Senior Planning Engineer, Bluewater, and different buoy loading/unloading Projects, Bluewater FPSO Modification, Water Technology

START Date
END Date
Experience Hours (Planning & Scheduling)
8200
Experience Hours (Cost Management)
0
Experience Hours (Forensic Analysis)
0

-       Review of hand-over documents and develop detailed project schedules and performance baselines

Senior Planning Manager - PMO (Dubai Metro and Tram O&M), Transport BU, Serco, Several Rail Transport Projects across Middle East

START Date
Experience Hours (Planning & Scheduling)
5000
Experience Hours (Cost Management)
500
Experience Hours (Forensic Analysis)
200

Initially appointed as the Planning Manager, Program Management Office (PMO) – Dubai Metro and Tram O&M Contract to spearhead the planning, reporting and programme development functions of PMO, later promoted to Senior Planning Manager to lead the planning and reporting activities for ongoing/upcoming rail projects in the Middle East.

 

Portfolio Planner, Fives Solios, EMAL ALuminium smelter phase 2, ALCAN Kittimat, EMAL LMT

START Date
END Date
Experience Hours (Planning & Scheduling)
2000

Portfolio Planner

Responsible for developing, maintaining and updating all plans and schedules for different projects (using Primavera P6) and provide analyses on Resources, Risk, Purchasing, Schedule, while controlling the project life cycle. Report progress to the Client and internally for Engineering, Manufacturing, Procurement, Delivery and Installation of equipment.

Senior Projectcontroller, PM Basics B.V., Several IT projects

START Date
Experience Hours (Planning & Scheduling)
3500
Experience Hours (Cost Management)
21000

Senior Projectcontroller. Specialism: project performance management (earned value management). Project, Program & Portfolio management, PMO, Cost management.

Senior Planning Engineer (PMC), The Louis Berger Group, Warner Bros. Theme Park & Ferrari World Phase II Projects

START Date
Experience Hours (Planning & Scheduling)
1700
Experience Hours (Cost Management)
200
Experience Hours (Forensic Analysis)
100

Senior Planning Engineer (PMC):

 

PLANNING ENGINEER, HNE Consultants, & Oil & Gas Projects 2) Buildings 3) Infrastructure

START Date
Experience Hours (Planning & Scheduling)
2800
Experience Hours (Cost Management)
2800
Experience Hours (Forensic Analysis)
2000

 

Planning Engineer

   Preparation of Daily, Weekly & Monthly reports which includes Manpower, Equipment, Material and important activities.

·        Coordinating with different departments like Civil, Architecture, Mechanical and Electrical for close monitoring of Progress & Manpower.

·        Improving Day to Day Project efficiencies by adapting Latest Technologies.