Forensic Planner / Delay Analyst, Lend Lease, Cape Lambert Rail Expansion Earthworks
Forensic Planner(3 months full time & as required through Mediation process), 6/2013 to 2/2014
Defense and implementation support for “Extension of Time” claim
Selected Accomplishments:
Introduction of Bill of quantities values of various types of earthworks values from estimates into various Primavera updated schedules.
Conversion of various earthworks units of measure into “Mass Haul” values and re-introduce these values into various updated schedules.