Create Detailed Schedule

PLANNING ENGINEER, Saudi Oger Ltd., King Abdullah Wagf Project

START Date
END Date
Experience Hours (Planning & Scheduling)
4750
Experience Hours (Cost Management)
250

1.Contract documents study.

2.Detailed Time Schedule.

3.Resources & Cost loading.

4.Updating, Monitoring & Controlling.

5.Progress reports.

6.Tracking issues.

7.Report & assest preparation of Claims.

8.Recovery Schedule.

9.Site coordination for civil works.

Planning and Controls Engineer, Archirodon Group NV, Synchrolift Project

START Date

Responsibilities:

  1. Develop Detailed Baseline Schedules.
  2. Monitor Project Progress and Prepare Monthly Progress Reports.
  3. Perform Delay Analysis Using Different Techniques.
  4. Risk Analysis.
  5. Prepare Preliminary/Tender/Design Schedules