Contract Documentation

Construction Inspector, Office Engineer, Alexander Potter & Associates / Camp Dresser & McKee, City of Baltimore

START Date
END Date

I served as Office Engineer and Construction Inspector on Patapsco Wastewater Treatment Plant expansion program, worth $100 million plus.  Program consisted of expansion of wastewater treatment facilioty to 70 mgd.  Maintained field records for inspection and equipment documentation.  Inspected offsite utility contract and onsite pile-driving operations.

Claims Analyst, CT Summation Case Management Database, Senior Construction Consultant, TDF, LLC, Washington Metro Area Transit Authority Orange Line Extension Claim

START Date
END Date
Experience Hours (Planning & Scheduling)
800
Experience Hours (Cost Management)
0
Experience Hours (Forensic Analysis)
500

Construction Consultant, P5 As-built scheduler for defense $30M litigation of $200M WMATA project; CT Summation software

§  25,000 activities scheduled from inspection dailies into as-built

§  Develop codes and filters, code activities 8 ways, global code changes for improved as-built analysis

§  Review business processes, spec and 300K image project record for claim analysis

§  First draft of report summarily ended claim, adjudication lower than owner’s initial offer