Claims Risk Assessment & Reporting
Claims Manager, Evans & Peck, ARTC South Sydney Freight Line
START Date
END Date
Assessment of Various Contractor's EOT claims on large Freight Line Project in Sub-urban location running through 26 Local Council Jurisdictions and complicated by numerous utility services buried throughout the site.
Claims Manager, Evans & Peck Pty Ltd, Woodside PLUTO LNG Plant
START Date
Analysis and assessment of extension of time claims in complex LNG Mega-Projects using critical path and dynamic methods.