Claims review/build/analyze

Forensic Planner, Brookfield Multiplex, Maundering Weir Water Treatment Plant Project

START Date
END Date
Experience Hours (Forensic Analysis)
750

Maundering Weir Water Treatment Plant – 165,000 Cubic Meters of water per day Water Treatment Plant.

Forensic Planner, (Specific Assignment), 02/2012 to 06/2012

Integrate Bill of Quantity data to progress schedules to assist client in development of Extension of Time claim case due to large change in scope and delay in design

Forensic Planner, Ertech, Marandoo Dewatering Project

START Date
END Date
Experience Hours (Forensic Analysis)
1250

Marandoo Dewatering Project – 24km pipeline with 27 bore pumps, Transfer & booster pump stations in Western Australia.

Forensic Planner, (Specific Assignment) 06/2013 to 03/2014

Preparation of Extension of time claim and support in Mediation process and conclusion

Forensic Planner, Ertech, Chevron Wheatstone Project

START Date
END Date
Experience Hours (Forensic Analysis)
150

wheatstone villageChevron Wheatstone Construction Village Buildings & utilities Project. Western Australia.

Forensic Planner, (Specific Assignment), 01/2014 to 03/2014

Preparation of Extension of time claim schedule in “Impacted as Planned” format.

Forensic Planner, PIHA, RIO-TINTO Cape Lambert Expansion Project

START Date
END Date
Experience Hours (Forensic Analysis)
600

RIO-TINTO Cape Lambert Services Contract Construction Project of Piping and Cable infrastructure at Point Sampson in Western Australia.

Forensic Planner, (Specific Assignment), 08/2013 to 06/2014

Preparation of Extension of time claim and support in Mediation process and conclusion