Q6 Senior Planning & Controls Consultant, Turner & Townsend Ltd, Baggage Upgrade & Asset Replacement of HBS3 Machines

START Date
END Date
Experience Hours (Planning & Scheduling)
2200
Experience Hours (Cost Management)
200
Experience Hours (Forensic Analysis)
0

As part of Heathrow’s Q6 programme of works all HBS3 Standard 2 machines have to be upgraded to meet new International Security requirements. These are being upgraded to HBS3 Standards, and due to space availability the Single Image 2 machine process has been adopted in T1. The works involve strip out of the IDL Terminal and replacing it with a completely new baggage hall and OOG functionality.

Senior Baggage Planning Consultant, EC Harris UK, Baggage Voids Refurbishment / Pier 5 Re-Modernisation / NOOG & TOOG Replacement Projects

START Date
END Date
Experience Hours (Planning & Scheduling)
1500
Experience Hours (Cost Management)
100
Experience Hours (Forensic Analysis)
0

All these projects revolved around either complete Aeroplane Taxi Apron civil breakout and re-enforcement of high load precast concrete units that formed the aircraft loading and standing structures. Extensive buried services radar scanning and excavation of contaminated grounds work. Any Drainage capacity increase required through means of using Underground Mole boring machines in conjunction with access pits.

Senior Planning Manager / Complex Build Integrator, MACE GROUP LIMITED, T1 Baggage Replacement Heathrow Airport

START Date
END Date
Experience Hours (Planning & Scheduling)
2100
Experience Hours (Cost Management)
150
Experience Hours (Forensic Analysis)
150