%26 project planning 2)cost planning 3)primavera p6

Start-up Planner, BECHTEL, APLNG

START Date
Experience Hours (Planning & Scheduling)
1500
Experience Hours (Cost Management)
500
Experience Hours (Forensic Analysis)
500

CSU Field Planner – Australia Pacific LNG

Project –          Australia Pacific LNG Project, Curtis Island, Queensland, Australia

Green field LNG project with 2 trains of liquefaction facilities, 2 LNG storage tanks, marine jetty and associated OSBL facilities. With the first two gas production trains processing capacity up to 9 million tons per annum.

Asst. Planning Engineer, Larsen %26 Toubro Construction Co., Chennai Metro Rail Project

S
Subash A 👤 Member for 10 years 9 months
START Date
Experience Hours (Planning & Scheduling)
2000
Experience Hours (Cost Management)
2000

1)Monthly progress report
2) Daily progress report
3) Dashboard
4) Monitoring progress
5) Estimating cost
6) Job Cost Report
7) Budget
8) Risk review

Budget & Cost Control Engineer, Freeport Mcmoran Indonesia, Mining infrastructure, conveyor and crusher

START Date
END Date
Experience Hours (Planning & Scheduling)
1000
Experience Hours (Cost Management)
2000
Experience Hours (Forensic Analysis)
2000

To control the cost in the project, create monthly and weekly cost report, daily monitoring of WBS

Acting Planning Manager, OIEC COnsortium, Gase refinery phase 20 & 21 south Pars gas field

START Date
END Date
Experience Hours (Planning & Scheduling)
800
Experience Hours (Forensic Analysis)
200

Location                      : Assalouye, Iran



Job Responsibility      : Scheduling, technical office managing, report control, claim managing, Site visit, Site management, claim management, Risk Control