Civil Site Engineer, Meimar Store Company, RESIDENTIAL VILLAS
Work As Site Engineer , execute ,reviewing and supervise labour and work at site .
Work As Site Engineer , execute ,reviewing and supervise labour and work at site .
Work As Site Engineer , execute ,reviewing and supervise labour and work at site .
Planning Engineer at Roy Hill Project in Australia.
Developed project baseline schedule.
Project progressing report.
November'11 to July'13 with M/s Petrofac Emirates, Ruwais, Abu Dhabi, as Engineer-Project Controls.
Project Title : Ruwais NGL Train 4 Project
Integrated decommissioning Program (Mega-project) activities maintaining (1-st and 2-d levels):
Strategic planning group leader
Integrated decommissioning Program (Mega-project) decommissioning scenarios (what-if scenarios) developing. Modelling and studying of different negative impacts or restrictions on total cost and critical path. Among those are inflation impact, technical uncertainties, funding lack and others. Developing new proposals for decommissioning strategy yearly update process.
Project Manager Professional (PMP)
Trainer in Project Management . Durang moré than 15 years I have been the CEO of a PMI Global Register Education Center. I had moré than 7.500 Professional students.
Helping them to manage their Professional Projects.
Project Manager Professional (PMP)
Trainer in Project Management . Durang moré than 15 years I have been the CEO of a PMI Global Register Education Center. I had moré than 7.500 Professional students.
Helping them to manage their Professional Projects.
Planning and controls management over a 35 year period with several major contractors in th UK and abroad
In addition , qualified with OND in 1982 ; again with BSc in 1986 and then with Phd in 1994 .
Similarly , progressed through the IOB from Student/Member/Fellow in the same timescales
Site Planner – June 2013 to August 2015
Faithful+Gould, Project Control Department
Tel: +966 14628770 Fax: +966 14611790, www.fgould.com
Project: New King Abdul Aziz International Airport, Jeddah, Saudi Arabia
Client: General Authority of Civil Aviation. Saudi Arabia
Consultant: Dar Al Handasa Group
Main Contractor: Saudi Bin Laden Group