%100- Project Planning; Progress Reporting; Primavera P6;

Sr. Engineer - Planning, Punj lloyd Sdn. Bhd., RAPID - Refinery And Petrochemical Integrated Development Project

START Date
Experience Hours (Planning & Scheduling)
4550
Experience Hours (Cost Management)
8150

Experience in

a. Planning & Scheduling : 4500 Hrs approx

i) Computing the weekly activities as per the Target % requirement.

ii) Simulation & 8 weeks look ahead/ forecasting.

iii) Progress Monitoring & Reporting. Highlighting the Project Manager of the delay in activities.

iv) S-curve updation of Physical progress on weekly basis.

v) Scrutinizing Schedules from the proposed Subcontractors to check its compatibility with Master Schedule.

Planning Engineer, Conoco Phillips Indonesia, East Hub Mercury Removal Gas/Water Project

START Date
END Date

May 2008 – Oct 2010 PT ISTECH RESOURCES ASIA (IRA)
Seconded to PT. CONOCO PHILLIPS INDONESIA as PLANNING ENGINEER for FEL 3 Engineering Phase for some projects in PT Conoco Phillips Indonesia; Eastern Hub Mercury Removal Gas/Water Project, Belanak LPG FSO and Belida FSO.
• Developed Overall Project Schedule as the COPI/Company schedule.
• Review overall project level 3 schedule submitted by bidders as part of Technical Bid Evaluation.