Pakistan (AS.PK)

PK

Project Coordination Manager, UMAG Technologie GmbH on their project for 30 MW Cogen Power Plant at Pakarab Fertilizer Ltd. Pakistan, 30 MW Cogen Power Plant at Pakarab Fertilizer Ltd. Pakistan

START Date
END Date

Worked as Project (Coordination) Manager in Umag Technologie GmbH for their project (# 875/07) at Pak Arab Fertilizer Ltd -
30MW Cogeneration Power Plant in Multan – Pakistan, and was responsible for erection / installation of all three HRSG’s &
coordination during commissioning and handover business.

Successfully managed and complete the project within allocated time by efficiently managing the workforce (>250 including engineers to layman) by proper planning, monitoring, timely decisions & providing workable solutions.

Core Team Senior Planning Engineer, Descon Engineering Limited, BHP Zamzama Field Expansion Project, Combined Cycle Power Plant

START Date
END Date
Experience Hours (Planning & Scheduling)
2000
Experience Hours (Cost Management)
2000

Resolution of issues in the implementation of Project Management Systems

Coordination with site project planning team

Resolution of recourse requirement issues

Progress Reporting to stakeholders

Jr. Engineer QC, TECHNO Engineering & Petroleum Services (Pvt) Limited, White Oil Pipeline Project. WOPP (865 Kilometers Cross-country Pipeline)

START Date
END Date
Experience Hours (Planning & Scheduling)
2800
Experience Hours (Cost Management)
0
Experience Hours (Forensic Analysis)
0
  • Manage all the activities regarding welding processes, procedures and Non-destructive Testing (NDT)
  • Manage all testing and inspection as per specified standard for pipe fabrication.
  • Check and manage all the activities regarding manufacturing & inspection of High Pressure Steel Line

    Pipe According to <?xml:namespace prefix = st1 />API-5L.

  • Implement the Quality Management System (QMS) as per PDCA Cycle.
  • Coordination regarding Material Management System (

PLANNER /SCHEDULER, China Petroleum Engineering & Construction Group-CPECC, White Oil Pipeline Project (WOPP) (865 Kilometers Cross-country Pipeline)

START Date
END Date
Experience Hours (Planning & Scheduling)
2450
Experience Hours (Cost Management)
0
  • Plan and extract weekly / monthly look a head schedules updates & analysis.
  • Identify all critical paths within a project by using float path analysis.              
  • Detail working schedule for the arrival of equipment loading for the erection of planned equipment.
  • Allocate resources to activities using distribution curves to accurately reflect how the work is performed.
  • Analyze changes between versions of schedules with Claim Digger to understand the progress that has tak

Assistant Executive, A H - CONSTRUCTION CONSORTIUM, ● Power Plant ● Cement Factory ● Housing Colony ● Fast Food Chains ● Other Projects $ 100 Millions

START Date
END Date

P r e    T e n d e r   &   P o s t    T e n d e r   P l a n n i n  g ,  S ch  e d u l i n g ,  P r o g r es s  - T r a c k  in g  ,   U p d a t i n g   ,   C o n t r o l l i n g   &   R e p o r t i n g

Sr. Planning Engineer Based at HO, MacDONALD & LAYTON CO. LTD. (MLC), INDUSTRAL PROJECTS ,MARINE PROJECTS ,INFRASTRUCTURE PROJECTS,UTILITY NETWORKS,TRANSPORTATION PROJECTS,POWER PLANTS & HEAVY ENGINEERING PROJECTS 2 Billions (Karachi - Pakistan)

START Date
END Date

CPM – Based Pre-Trader & Post Tender Planning Scheduling, Monitoring, Reporting including following                                                                                  &n

Section Engineer, MacDONALD & LAYTON CO. LTD. (MLC), Pak Suzuki Motor Assembly Plant $ 4 Millions (Karachi Pakistan)

START Date
END Date

Re s  p o s  i b l  e        f o r            P l a n n i n g         C o - o r d i n a t i o n           o f        a l l         s i t e                   a c t  i v i t i e s

Site Engineer at site, MacDONALD & LAYTON CO. LTD. (MLC), Pak Land Cement Factory $ 6 millions (Karachi Pakistan)

START Date
END Date

Re  s p o s  i b  l  e           f o r              F a b r i c  a t i o n        &      In s t  a l l a t i  o n      o f   a l l     St e e l    -  S t r u c t u r a l            w o r k s 

Assistant Engineer at site, MacDONALD & LAYTON CO. LTD. (MLC), 2x200 Mega Whatt - Thermal Power Station at Pipri $ 68 Millions (KARACHI - PAKISTAN)

START Date
END Date

 R e s p o n s i  b l e               f o r                 I n f r a s t r u c t u r e          &        A n c i l l a r i e s            S t ru  c t u r e  s