Pakistan (AS.PK)

PK

Project Director, IPECC Consultants, Creating a Project Management Office (PMO)

S
Shuja Ali 👤 Member for 15 years 11 months
START Date
END Date

 

Creating a Project Management Office (PMO)

Enables the Client to Perform More Consistently

A multinational company restructured its projects department to help it handle an ever-increasing load of projects. To ensure consistency in its performance, the projects’ heads decided to establish a Project Management Office (PMO). A PMO would set standardized processes to ensure that any project would be performed using the same high quality methods.

Senior Planning Consultant, IPECC Consultants, Tuwairqi Steel Mills - Providing Project Planning & Scheduling Services

S
Shuja Ali 👤 Member for 15 years 11 months
START Date
END Date

PROJECTS' EXPERIENCE

  1. Tuwairqi Steel Mills - Providing Project Planning & Scheduling Services

  • June 2007 to August 2007

In DRI project, Tuwairqi Steel Mills Limited (TSML) was looking for a firm to provide Project Management Consultants (Programs Manager, Project Managers, & Project Control Officers) to work closely with the client in order to manage & deliver the project with it Project Management methodologies, too

SAIFUR REHMAN

First Name
SAIFUR
Last Name
REHMAN
Years Experience
0
Telephone Number
+92(333)9795450

CURRICULUM VITAE

 

 

SAIF-UR-REHMAN

H. No. 11, Nasirabad Janoobi

Chenabnagar (P.C. 35460)

PAKISTAN

Contacts:

(i)           24/7 Cell phone:+92-333-9795450

Planning/Project Engineer, Engineering Kinetics Limited, Maple Leaf Cement Expansion, Pakistan (FL Smith Plant 3300 MTPD)

N
Nazir Ahmad 👤 Member for 19 years 3 months
START Date
END Date
  1. Plan & manage the resources ahead of time & monitoring the progress by network scheduling techniques Monitoring and control of man-hours on activity basis & Change orders with respect to contract
  2. Prepare, monitors & reviews work plans, programs and budgets
  3. Plans resources to achieve profit & productivity
  4. To generate cash flow and forecast reports of the project and compare with project budget
  5. Preparing & Segregation the Scope for Contractors, making comparative statements, analyzing & awarding contracts
  6. Pre

Project Engineer/ Planning Engineer, Engineering Kinetics Limited, PARCO Mid Country Refinery Project, Pakistan (100,000 BPD CDU)

N
Nazir Ahmad 👤 Member for 19 years 3 months
START Date
END Date
  1. Plan & manage the resources ahead of time & monitoring the progress by network scheduling techniques Monitoring and control of man-hours on activity basis & Change orders with respect to contract
  2. Prepare, monitors & reviews work plans, programs and budgets
  3. Plans resources to achieve profit & productivity
  4. To generate cash flow and forecast reports of the project and compare with project budget
  5. Preparing & Segregation the Scope for Contractors, making comparative statements, analyzing & awarding contracts
  6. Sup

Incharge Planning & Field Engineering , Descon Engineering Limited, Kadanwari Upgrade & Miano Field Development Project, Pakistan (200 MMSCFD)

N
Nazir Ahmad 👤 Member for 19 years 3 months
START Date
END Date
  1. Establish work break down structure for project
  2. Prepare, monitors & reviews work plans, programs and budget and resources to achieve profit & productivity
  3. To generate cash flow and forecast reports of the project and compare with project budget
  4. Prepare cost estimate plan& basis
  5. Preparing & Segregation the Scope for Contractors, making comparative statements, analyzing & awarding contracts
  6. Plan, monitor and control the 12” & 16” gas pipeline, which comply with ASME B31.8
  7. Planning & co-ordination wi

Project Engineer, JGC-Descon Limited (A joint Venture of JGC Corporation & Descon Engineering), Multiple Projects / Petrochemical ; Oil and Gas / EPC Project Controls

N
Nazir Ahmad 👤 Member for 19 years 3 months
START Date
END Date
  1. Preparation and presentation of technical and commercial proposal for engineering phase
  2. Preparation of Construction Scope of Work for ITB and requisitions for Package Equipments
  3. Coordination with design team for flow of information to main EPC contractor
  4. Review of P & ID’s, Plot Plans & General Arrangements drawings considering general ITB requirement
  5. Planning, Monitoring and control of engineering activities during detailed engineering phase
  6. Coordination with each discipline to manage timely information flow between concerned

Maintenance Planning Engineer, NOVATEX Limited Karachi, Pakistan, PETROCHEMICAL PLANT MAINTENANCE & EXPANSION PROJECTS

START Date
END Date

NOVATEX Limited Karachi, Pakistan                                                Jan, 2007 – March,2008

Planning Engineer

As the part of Mechanical & Utilities Department, my areas of responsibilities as a Maintenance Planning Engineer were the following: