planning engineer, IGS CORPORATION LLC, & Oil & Gas Projects
v Developing Level I, II, III Schedule and Micro Schedule in Primavera & MS Projects.
v Calculating Resource requirements like manpower and Plant & Machinery requirements for the Estimation in ITB.
v Liquidating the Project quantitatively across the duration as per schedule.
v Micro- scheduling (Level-4) & Plan development for the site for specific locations and specified activity.
Kuanysh Bekbauov
PLANNING ENGINEER, “Kazakhstan Caspian Offshore Industries” LLP , Kashagan Field Development Project EP Offshore. Mechanical Completion
· Planning and schedule preparation for engineering, procurement, construction of Mechanical, Piping and Electrical, Instrumentation activities
· Responsible for monitoring progress of work and compares with the approved schedule.
· Daily monitoring the Status of Subsystems and Commissioning Units (ITR’s, DAC’s, MC-01 completion)
Jeanette Reyes
Scott Jordan
Planning Specialist, Karachaganak Petroleum Operating BV, Karachaganak Development Project – Phase II
Phase II involved an investment of over US$ 1 billion into the construction and enhancement of existing facilities, new gas and liquid processing and gas injection facilities, a workover program consisting of 100 existing wells, a 120 MW power station for the facilities, and laying a new 650 kilometre pipeline to connect the field to the Caspian Pipeline Consortium (CPC) system at Atyrau.
Support Services Manager, Agip KCO , Kashagan West Development – Experimental Programme
The project consists of the “Experimental Phase” (EP) of the field development and includes both on and offshore facilities valued in excess of US$ 36 billion. EP nominal capacity of 450,000 bopd. Program challenges include extreme climate variations, environmental issues, diverse and multi-cultural project team, high H2S content combined with high pressure in a SIMOPS environment and global work sites for design, fabrication and construction activities.
Jose Emmanuel Clamar
Lead Planning & Project Control Engineer, CAEL - Chiyoda Almana Engineering LLC, RasGas Long Term EPCm Project
Check, reviews and analyzes all Level II project schedule (FEED & EPCm) using Primavera 6 (P6) for various projects prepared by assigned Controls Engineer for Service Proposal and Level VI schedule upon receipt of Service Order (SO) from the Client for implementation. Check & reviews Cost Time & Resources (CTR) prepared by assigned Control Engineer prior to submission to Client. Check & reviews Progress Measurement Unit (PMU) for each projects. Participates in the Technical / Commercial Bid Evaluation (TBE/CBE) of the Bidders for various projects.