Western Australia (OC.AU.WA)

AU

GHD Lead Planner

Mining: (Iron Ore) Non Process Infrastructure Engineering Design Schedule inclusive of Selection Phase Study Schedule, Detailed Design Schedule and Execution Schedule which feed into client master schedule.

Weekly reporting cycle to client:

- Fully resource loaded shedule 3600 activites

- Earned value management

- Percent complete; estimate units and days to completion

- report on potential problems and schedule overruns



Water: Full EPCM schedule for Iron Ore Mine



Oil and Gas: FPSO Schedule Concept through to First Gas

Construction Project Planner / Senior Planner, Monadelphous Engineering Associates, Construction & Mining

START Date
END Date
Experience Hours (Planning & Scheduling)
40000
Experience Hours (Cost Management)
0

•Preparation of Primavera Level 4 overall schedule for BHP Biliton Iron Mines Expansion

•Preparation of Claim Schedule base in the impact of delays.

•Analysed the base line and current Level 4 Schedule.