Mining: (Iron Ore) Non Process Infrastructure Engineering Design Schedule inclusive of Selection Phase Study Schedule, Detailed Design Schedule and Execution Schedule which feed into client master schedule.
Weekly reporting cycle to client:
- Fully resource loaded shedule 3600 activites
- Earned value management
- Percent complete; estimate units and days to completion
- report on potential problems and schedule overruns
Water: Full EPCM schedule for Iron Ore Mine
Oil and Gas: FPSO Schedule Concept through to First Gas