Advisor Planning - Sr Planning Engineer, Projeqz, Down Town Jabel Ali

START Date
END Date
Experience Hours (Planning & Scheduling)
4000
Experience Hours (Cost Management)
1000
Experience Hours (Forensic Analysis)
2000

 

Project                        :           DownTown Jebel Ali - 2 Blocks Office and 2 Blocks of

Ansuman Satapathy

First Name
Ansuman
Last Name
Satapathy
Professional Since
Oldest experience
Years Experience
12
  • A reputed Project Manager with 22 years of experience in Strategic Planning, Project Management, Consultancy, Site Management and Techno-commercial Operations covering Industrial, Public (Hotel & Shopping Mall), Residential Buildings, Road and Different Types of Infrastructure, Marine and Railway Projects
  • Currently working with Shapoorji Pallonji Mideast (LLC) as Deputy General Manager – Head of UAE Planning
  • History of  concurrently directing multiple as well as large size projects to successful completion through effective management and team collaboration; co

Lead/Senior Planning Engineer, Al Habtoor Engineering Enterprises, 170 Public Villas at Al Samha, Al Raha Beach Resort (5 Star Hotel & Shopping Mall, Dubai Marina Terrace – A 38 Storied Tower)

START Date
END Date
Experience Hours (Planning & Scheduling)
9200
Experience Hours (Cost Management)
1500
Experience Hours (Forensic Analysis)
3000
  • Anchored on-site construction activities to ensure completion of project within the time & cost parameters.

Head of Planning & Scheduling, Al Geemi & Partners, •New Clusters / Service Buildings and Miscellaneous Facilities at Asab for ADCO, •Construction of Married Staff Accommodation, Facilities & Related Infrastructure at Ruwais for ADNOC, •Roads & Utility Wo

START Date
END Date
Experience Hours (Planning & Scheduling)
3400
  • Evaluated & determined appropriate construction delivery systems and most cost-effective plan / schedule for completing the project
  • Created the manpower histogram & cash inflows to find out the resource availability and the different options to arrange the remaining resource
  • Tracked the different delay events and prepared the EOT claims, accordingly
  • Actively involved with their projects, as per the request from the ADNOC and ADCO managements

Head of UAE Planning Division, Shapoorji Pallonji Mideast LLC, Business Park - Dubai Hills, Cayan Cantara, etc, Imperial Tower, Kings College Hospital, Marina Development, MBR - Park Heights, Palm Gateway

START Date
Experience Hours (Planning & Scheduling)
8000
Experience Hours (Cost Management)
2000
Experience Hours (Forensic Analysis)
4000
  • Develop project baselines ; monitor and control projects with respect to cost, resource deployment, time over-runs and quality compliance to ensure satisfactory execution of the assignments
  • Administer overall management of Planning Department of UAE Business Unit; prepare EOTs for all the projects under UAE Division
  • Take care of the Planning Department with team of over 30 Engineers entailing Planning Managers, Senior Planning Engineers, Planning Engineers and Junior Planning Engineers
  • Review designs, drawings, specifications, BOQ & modifications required to

Head of UAE Planning Division, Shapoorji Pallonji Mideast LLC, Palm Gateway, Kings College Hospital, Marina Development, Cayan Cantara, MBR - Park Heights, Business Park - Dubai Hills, Imperial Tower, etc

START Date
Experience Hours (Planning & Scheduling)
8000
Experience Hours (Cost Management)
2000
Experience Hours (Forensic Analysis)
4000
  • Develop project baselines ; monitor and control projects with respect to cost, resource deployment, time over-runs and quality compliance to ensure satisfactory execution of the assignments
  • Administer overall management of Planning Department of UAE Business Unit; prepare EOTs for all the projects under UAE Division
  • Take care of the Planning Department with team of over 30 Engineers entailing Planning Managers, Senior Planning Engineers, Planning Engineers and Junior Planning Engineers
  • Review designs, drawings, specifications, BOQ & modifications required to

Vijay Prakash

First Name
Vijay
Last Name
Prakash
Professional Since
Oldest experience
Years Experience
11
Telephone Number
+971529978668
LinkedIn Profile
https://ae.linkedin.com/in/vijaydoddabela
Facebook Profile
Vijay Prakash

I have had 13+ years of work experience in Project Planning & Scheduling using MSP / Primavera 6 and  had experience in various development of Project Charters, Project Scope Statement & Project Management Plan for Initialization, Planning & Execution, updating & scheduling program on weekly basis, delay analysis (Effect & Impact on Schedule), mitigation & acceleration plans using Primavera 6, preparing EOT’s  and close project.

Deputy Planning Manager –Planning & Operation Support Department, Shapoorji & pallonji MiD EAST, LANDMARK HEAD QUARTERS 3B+G+7P+19+3R

START Date
END Date
Experience Hours (Planning & Scheduling)
4000
Experience Hours (Cost Management)
4000
Experience Hours (Forensic Analysis)
400
  • Responsibilities: Assigned in Multiple projects, involved in Pre-tender Technical Submission & Developed post Contract projects Cl.14 Baseline Program & obtained approved within the stipulated time.
  • Preparation of Weekly Progress PPT’s & Dashboards for the Weekly Progress review meeting with the Consultant.
  • Highlighting the Critical Activities and provide look ahead programs & Mitigation plans to the Project Team.
  • Progress monitoring of the performance of project through the Earned Value Analysis.

Planning Engineer, ACC, B+G+2P+22/23 story Residential complex , Business bay, Dubai, UAE

START Date
END Date
Experience Hours (Planning & Scheduling)
2000
Experience Hours (Cost Management)
2000
Experience Hours (Forensic Analysis)
400
  • Responsible for developing high level deliverable schedule, detailed project plans & Authorities Inspection & Approval Schedule.
  • Project Schedule Development: Progress & Productivity Measurement, “S” Curves, KPI’s & Performance Dashboards.
  • Preparation of Labor Histograms, Resource & Cost loading & Cash flow generation.
  • Preparation of Accelerated Program, Mitigation Plans in case of Delay events & Reviewing Subcontractor’s Program.
  • Progress monitoring of the performance of project through the Earned Value Analysis.<