Planning Engineer, Saudi Oger Ltd., KAEC - King Abdullah Economic City.
- Monitoring of the programme and re-planning - if needed – during the project life cycle.
- Prepare, review and issue daily, weekly and monthly reports as per the contract and the required internal reports to Project Manager (PM) and/or management to highlight areas of concern, programme slippage and project performance indices (KPI).
- Prepare two weeks look ahead schedule and distribute to construction team and follow up / support to achieve it.
Engineer / Project Engineer, Medad for Urban Development Co., Sahl Bin Al-Rabea Primary School
- Preparing project programme using (Primavera V3.1).
- Monitoring the execution of all works as per specifications.
- Controlling the manpower, materials, equipment and the running of the site works as per schedule.
- Site handing over.
Sherif Saleh
- Primavera P6
- Project Control
- Project Planning
- Construction Management
- Cost Engineer
- Cost Control
- CPM Scheduling
- EPC
- Cost Management
- Subcontracting
- Infra Structure
- Cash Flow
- Progress Monitoring
- Productivity
- High Rise
- Tilos
- Autocad
- Excel
- Revit
- Navisworks
- MS Project Planner
Planning Manager, ROOTS STEEL INTERNATIONAL, SAUDI ARABIA, King Abdulaziz International Airport(KAIA), Jeddah,
- Analyze,reviewandcommentonEPCCcontractor’sschedule
- Analyzeandreviewthecriticalpathandresourcesallocation,utilizingproductionrateandadjacentdurations
- Identifypotentialrisks,maintainariskregisterandsuggestmitigationplan
- Developphysicalprogressmeasurementsystem(PPMS)
Project Control Engineer, "AL AYUNI TRADING AND CONTRACTING COMPANY RIYADH,", Tama Bypass Link Phase-2
- Prepare and update project schedule based on the contract.
Syed Akhlaq Hashmi
PMP,Delay Analysis,Forensic Analysis,TilosPrimevera-P6,Share Point,MS Project,Auto Cad,MS Office
Program Planning Manager, INECO, Haramain High Speed Railway Project Phase -2 Jeddah
Date From Oct 2013-June 2017 / Employer- INECO - Jeddah
: Program Planning Manager
Project: Haramain High Speed Railway Project Phase -2 Jeddah
Client: SRO.
Responsibilities:
Project Controls Manager, INECO, Infrastructure Project
Date From June 2017 to present / Employer- Al Salomi Company
: Project Controls Manager
Project: Infrastructure Project
Client: Royal Commission - Jubail
Responsibilities:
deputy project director, Saudi Bin Laden Group, jeddah tower" highest tower 1008 m"