Planning Engineer, IMCO Engineering & Construction Company, Oil & Gas Pipeline, Storage Tank, Bulding, Electrical & Instrumentation, Flare, Injection Quills

START Date
  • Preparation of the Project Master Schedule, Summary curves.
  • Preparation of detailed Project Execution Plan, S-Curve, Resources and Manpower Histogram in Consideration with the Site logistic Plan.
  • Preparation of Recovery schedule as required.
  • Preparation of Tender & Shutdown Schedule.
  • Preparation of Asset capitalization, Data Acquisition (CMMS) for SAP, Close out Report, Invoices & Project Dossier.
  • Preparation, Review & Publishing of MIS & Monthly, Weekly, daily reports and Presentations, using bar Charts, S-­Curve and presenting t

Fluor Daniel Consultants-Kuwait Project Controls Engineer

Project I - DOW / PIC Olefins II Project, DOW / PIC, Kuwait – USD - 3 Billion$ Project Kuwait

•     850 kta Ethane Cracker (EU2), 600 kta EO/EG Plant (EO/EG2)

•     450 kta EB/SM Plant (EBSM), 225 kta Expansion of existing Equate Polyethylene Trains

•     1,500 ton per day Oxygen Plant (Air Separation Plant - ASU2)

•     Expansion of Equate Utilities & Infrastructure (U&I)

•     New Shared Utilities & Infrastructure with Aromatics (ARO)