SLP Engineering Planning Engineer

Initially responsible for the development of the Commissioning Schedule for the SCott Platform LQ. Working with the Commissioning Manager.

Transfering to a corporate role for the development of all Planning input to tenders. The major ones of which included:

THE DESIGN, BUILD & OPERATION OF AN FPSO FOR AMERADA HESS.

THE HOOK-UP & COMMISSIONING OF OFFSHORE PLATFORMS FOR ESSO MALAYSIA.

Foster Wheeler Energy UK Senior Planner

Senior Planning Engineer assisting in setting up and monitoring the Front End Engineering for a major refinery in NW India for IOCL. The FEL started in Dec 06 and was completed in March 2008. I was responsible for assisting in setting up the Level 3 Schedule using Primavera P5 & monitoring the Progress of the project. Milestones & DMS were also used to monitor progress of the documentation.