Senior Planner, VolkerFitzpatrick, Southwark Waste Treatment Facility / Reading Station Redevelopment

START Date
END Date
Experience Hours (Planning & Scheduling)
3000
Experience Hours (Cost Management)
500

Southwark Waste Treatment Facility

Developing Tender Program into a relevant and workable target program (Asta)

Ensuring interdependencies between civils and builiding where identified and managed

Managing client expectations

 

Reading Station Redevelopment

Managed a planning team

Developed and maintained fully cost loaded contract program

Planner, Balfour Beatty, EAST LONDON LINE - VALUE: 450m GBP

START Date
END Date
Experience Hours (Planning & Scheduling)
4000
Experience Hours (Forensic Analysis)
400

Design Planner - Planning, co-ordinating and prioritising design packages 

Construction Planner - Civils and Infrastructure - Providing planning support for Three Bridge Replacements, Four Station Escape Stairs, One Rail Junction and Two Major Pipe Protection Structures

Comms Engineer

Senior Planning Consultant, Atkins Faithful & Gould, High Speed 2

START Date
END Date
Experience Hours (Planning & Scheduling)
400

Built the strategic programme for the development of the HS2 alignment, structures and environmental mitigations required to support the Environmental Statement and associated documents for public consultations and Hybrid Bill submission

Senior Planning Consultant, Atkins Faithful & Gould, Crossrail Farringdon - C435

START Date
END Date
Experience Hours (Planning & Scheduling)
1050
Experience Hours (Forensic Analysis)
450

- Critical Path Analysis

- Extension of time assessments

- KPI Reporting

- Maintaining key interdependencies between projects/programmes

Assistant Planning Engineer, Metisplan Ltd, (various projects) @ all UAE.

START Date
Experience Hours (Planning & Scheduling)
650
Experience Hours (Forensic Analysis)
100

Metiplan Ltd - Progress reporting across a range of Construction Sites, Tender planning & Logistical plans, Programme development - logic sequencing & time frame estimations, Developing skills in hook time analysis methods. 4D Training through Synchro Software.

Armando Flores

First Name
Armando
Last Name
Flores
Professional Since
Oldest experience
Years Experience
46
Guild Accreditation
Awaiting Applicant
Telephone Number
00584245377784

Experienced in project cost control, budget formulation & execution, planning & scheduling, business valuation, “Excel” financial & logistic modeling, and treasury in the Oil & Gas industry (upstream and downstream), and construction.

Cost Manager for the Programme Office, BECHTEL, Tubelines Upgrade

START Date
END Date
Experience Hours (Cost Management)
9250

Tube Lines (Bechtel and Amey / Ferrovial) has won a 30-year concession of London Underground’s Jubilee, Northern, and Piccadilly lines under the PPP/PFI, to improve and maintain the infrastructure of these lines.