/ Construction Project Planner / Senior Planner, Bouygues E&S UK Ltd, Data Centers

START Date
Experience Hours (Planning & Scheduling)
17300
Experience Hours (Cost Management)
10550
Experience Hours (Forensic Analysis)
800

Bouygues Energies & Services Contracting, London
Project Planner, May 2018 to Present
Formulate a pre-construction/construction, commissioning programme and a methodology at tender stage. Create fully resource loaded and baselined project programmes for major phases of the project, including design, installation and commissioning, milestones capturing key dates, and client deliverables, based on agreed WBS.

/ Construction Project Planner / Senior Planner, Bouygues E&S UK Ltd, Data Centers

START Date
Experience Hours (Planning & Scheduling)
17300
Experience Hours (Cost Management)
10550
Experience Hours (Forensic Analysis)
800

Bouygues Energies & Services Contracting, London
Project Planner, May 2018 to Present
Formulate a pre-construction/construction, commissioning programme and a methodology at tender stage. Create fully resource loaded and baselined project programmes for major phases of the project, including design, installation and commissioning, milestones capturing key dates, and client deliverables, based on agreed WBS.

/ Construction Project Planner / Senior Planner, Bouygues E&S UK Ltd, Data Centers

START Date
Experience Hours (Planning & Scheduling)
17300
Experience Hours (Cost Management)
10550
Experience Hours (Forensic Analysis)
800

Bouygues Energies & Services Contracting, London
Project Planner, May 2018 to Present
Formulate a pre-construction/construction, commissioning programme and a methodology at tender stage. Create fully resource loaded and baselined project programmes for major phases of the project, including design, installation and commissioning, milestones capturing key dates, and client deliverables, based on agreed WBS.

Planning Manager, Multiplex, Preconstruction

START Date
END Date
Experience Hours (Planning & Scheduling)
950

Tender Planning 

In my short time at multiplex I have worked on two significant tenders including the fit out of the new HQ for a large tech company in the Battersea power station as well as £350m residential development in Canary Wharf. Unfortunately, because of covid- 19 and the effect on the portfolio of work undertaken by Multiplex I was included in their redundacies.  

Planning Manager, Multiplex, Preconstruction

START Date
END Date
Experience Hours (Planning & Scheduling)
950

Tender Planning 

In my short time at multiplex I have worked on two significant tenders including the fit out of the new HQ for a large tech company in the Battersea power station as well as £350m residential development in Canary Wharf. Unfortunately, because of covid- 19 and the effect on the portfolio of work undertaken by Multiplex I was included in their redundacies.  

Planning Manager, Multiplex, Multiple

START Date
END Date
Experience Hours (Planning & Scheduling)
950

Tender Planning 

In my short time at multiplex I have worked on two significant tenders including the fit out of the new HQ for a large tech company in the Battersea power station as well as £350m residential development in Canary Wharf. Unfortunately, because of covid- 19 and the effect on the portfolio of work undertaken by Multiplex I was included in their redundacies.  

Planning Manager, Multiplex, Multiple

START Date
END Date
Experience Hours (Planning & Scheduling)
950

Tender Planning 

In my short time at multiplex I have worked on two significant tenders including the fit out of the new HQ for a large tech company in the Battersea power station as well as £350m residential development in Canary Wharf. Unfortunately, because of covid- 19 and the effect on the portfolio of work undertaken by Multiplex I was included in their redundacies.  

Planning Manager, Multiplex, Multiple

START Date
END Date
Experience Hours (Planning & Scheduling)
950

Tender Planning 

In my short time at multiplex I have worked on two significant tenders including the fit out of the new HQ for a large tech company in the Battersea power station as well as £350m residential development in Canary Wharf. Unfortunately, because of covid- 19 and the effect on the portfolio of work undertaken by Multiplex I was included in their redundacies.