Project Cost Control Engineer, Greenstone Resources Corporation a member of Red 5 Limited, Siana Gold Mining Project

START Date

GREENSTONE RESOURCES CORPORATION (18 October - present)

A MEMBER OF THERED 5 LIMITED GROUP OF COMPANIES

L5, NOL Tower, Commerce Ave., corner Acacia Ave., Madrigal Business Park

Muntinlupa City, Philippines

www.greenstone.com.ph

 

  • SIANA GOLD MINING PROJECT/ SURIGAO DEL NORTE, PHILIPPINES

US$70M

 

PROJECT COST CONTROL ENGINEER

Ilya Lebedev

First Name
Ilya
Last Name
Lebedev
Years Experience
0

I am a planner in oil and gas engineering company. In the beginning of my biography as a plenner. Will be happy to get new useful information and experience via this website.

Hariadhi Anjar kusuma

First Name
Hariadhi
Last Name
Anjar kusuma
Years Experience
0
Telephone Number
+976-11-331880 ext 3138

I am 35 years old and Married. I have graduated Industrial Engineering from Institute Technology of 10 November Surabaya with satisfied predicate and have GPA of 3.13. I am started my career at PT PAL INDONESIA (Ship Building and Heavy Industries – please visit the web site www.pal.co.id) in Surabaya on June 1996 as a Supervisor Fabrication Process at Construction Department, in War ship division. And the same time of I am working.I am also studying until get college degree S1.

Graduate Planner, Research laboratory of Moscow University of Railway Communication, Post Graduate in National Economy Management

START Date
END Date

 

Research laboratory of Moscow University of Railway Communication (National Economy Management Department)

Undertook analytical research and development of Material & Manpower Resource Management system on a base of P3e/c.

Updated existing CTR library and linked it with MMRM system.

Developed mathematical module for decision support systems and conducted lectures and seminars to undergraduates

PLANNING ENGINEER, Lukoil-Neftegazstroy, Sakhalin 1

START Date
END Date

Sakhalin-1 Project

CM, FM, MM – Exxon Mobil – Oil Pipeline – Eastern Russia

The Sakhalin-1 Project includes three offshore fields: Chayvo, Odoptu, and Arkutun Dagi in Sea of Okhotsk.

Sakhalin-1 potential recoverable resources are 2.3 billion barrels of oil and 17.1 trillion cubic feet of gas (or 307 million tons of oil and 485 billion cubic meters of gas).

The Onshore Production Facility (OPF) started up in October 2006 and ahead of schedule, allowing ramp-up of oil production to a targeted peak rate of 250,

Senior Planner / Scheduler, Globalstroy-Worleyparsons-Zarubejneft Consortium, YK - Yuzhno Khylchuyu

START Date
END Date

YK Project (Yuzhno Khylchuyu)

PM, E, P, C – ConocoPhillips – Oil & Gas Project – Northen Russia

Yuzhnoye Khylchuyu (YK) field located 120 kilometers northeast of Naryan-Mar, 2300 kilometers northeast of Moscow o the Barents Sea coast. The project represents an investment of USD 1.5 billion.

The YK field development divided on two phases, the First Production Phase (Train No.