Quantum Consultant, Confidential, Undisclosed Confidential Projects
Production of expert quantum report for prolongation costs for critical delays between 2008 and 2011
FIDIC Red Book
Claim value circa €12 million
RO
Production of expert quantum report for prolongation costs for critical delays between 2008 and 2011
FIDIC Red Book
Claim value circa €12 million
Production of sub-contractor claim for disruption costs on Bucharest to Constanta rail project
Claim value circa €2 million
FORENSIC DELAY ANALYST ON MOTORWAY PROJECT IN EUROPE. MS PROJECT PROGRAMMES. REPORT WRITING AND DRAFTING CLAIM DOCUMENTS.
Delay Analyst on major bridge project.
Ms project.
DElay and disruption analysis.
Expert reports to DAB.
Delay analyst on Railway Project.
Producing expert opinion delay report.
Tilos and ms project software.
All major civils works.
. PROJECT CONTROL ENGINEER – Project Accounting, Cost Controlling & Contract Administration
2008 / 09 – 2011 / 07
SC SIMontaggi SRL – Industrial Construction SC SIMontaggi SRL is the Romanian subsidiary of SIM SPA Italy company. SIM SPA Italy is a privately owned mechanical construction company, specialized in the fabrication and erection of piping, structural steel, tanks and installation of rotating / static equipment and associated hoisting activities.
Specialties: