Assistant Planner or Planning Engineer, Samsung C & T, Underground MRT (Railway Station) Construction

START Date

Major Duties:

Ø  Prepare Weekly Internal Report for HQ including update of programme, quantity of excavation and backfill work done, concrete casting progress, progress layout in CAD, variance analysis;

Ø  Prepare Weekly LTA Report including tabulation of work done for struts installation and removal, excavation and backfilling, concrete quantity, brackets installation, architectural progress and progress layouts in CAD;

john mark galela

First Name
john mark
Last Name
galela
Professional Since
Oldest experience
Years Experience
3
Telephone Number
+65 83434367

I am a planner since 2010 up to date. I've been doing project schedule and monitor the project using P6 and excel, i also do methodology of the job, central monitoring system for a project and other related office job needed by the client. My current project is a planner in Hai Leck Engineering and been assigned for the Jurong TurnAround this coming october 2014 under exxon mobil.

Yin Htwe

Y
Yin Htwe 👤 Member for 12 years 6 months
First Name
Yin
Last Name
Htwe
Professional Since
Oldest experience
Years Experience
43

Primavera Planner with 3 years experience in refinery maintainance and 3 years experience in building & construction ( M&E ).

Planner, Rotary Engineering Limited, Singapore Parallel Train (SPT)

E
Eric Amagon 👤 Member for 12 years 6 months
START Date
END Date

Prepare three-week and one-week lookahead schedule with corresponding to availability o fmaterial and workfront.

Monitor and update project status.

Identify causes of delays in the projects.

Monitor/update daily manpower and manhours used for the project.

Prepare/update daily monitoring drawing checklist.