MMC OIL & GAS ENGINEERING Planner
Current Role
MY
Primavera DOS version; planning, tracking, reporting, monitoring
Building works & higrise
Planning: Primavera P3; planning, tracking, monitoring, reporting, cashflow, EV, forecast, etc.
Sectors: Power transmission substation generation , railway, civil engineering, building highrise, mechanical & electrical
Overall planning: Primavera 3; plan, track, monitor, report monthly, EV, cashflow,
Large Housing scheme & infrastructure projects
Project Control Plan and Related Procedures, Planning/Scheduling, Earned Value Management, WBS and Cost Control, Progress Reporting, Variations and Claim Analysis.
· Worked as Project Services Lead for Husky Liwan Project IPT (Integrated Project Team – Owner’s Team) team member.
Project : Engineering, Procurement, Construction and Commissioning
(EPCC) of New 50HN Nitrogen Plant.
Location : MLNG 3 SDN BHD, Bintulu, Sarawak, MALAYSIA.
Project : PDH & PORT STORAGE 3rd Plant Turnaround 2007
Location : MTBE MALAYSIA SDN BHD, Gebeng, Pahang.
Project : VCM & PVC 3rd Major Turnaround 2006
Location : VINYL CHLORIDE MALAYSIA SDN BHD (VCMSB)
Kerteh, Terengganu.
Project : PASB 3rd Plant Turnaround 2006
Location : PETRONAS AMMONIA SDN BHD (PASB)
Kerteh, Terengganu