South Africa (AF.ZA)

ZA

Junior Planner / Scheduler, Wetback , Medupi Low Pressure Services

START Date
Experience Hours (Planning & Scheduling)
1000

Update P6 weekly with information received from site, build Excel spread sheets with progress from each week. Build weekly reports about delays and progress. Build proposals for claims and new work.

Junior Planner / Scheduler, Wetback , Medupi Low Pressure Services

START Date
Experience Hours (Planning & Scheduling)
1000

Update P6 weekly with information received from site, build Excel spread sheets with progress from each week. Build weekly reports about delays and progress. Build proposals for claims and new work.

Assistant Engineer, Van Wyk en Louw Raadgewende Ingenieurs, Witbank to Middelburg Freeway and Waste Water Projects

START Date
END Date

Structural Design Engineer

1967 - mid 1968: 29 no. Manual design calculations for In-situ culverts on the (then) future Witbank to Middelburg freeway, from first principles to final drawings, in pencil, for submission to the Transvaal Chief Road Engineer. The drawings were traced in ink by qualified tracers before submission.

Structural Design Engineer, Coyne et Bellier Ingenieurs Conseil, Arch at Vanderkloof Dam and Cabora Bassa Dam

START Date
END Date

Working under the Project Leader for Arch Dams in the firm, I participated in the structural design of two large arch dams which were due to be built in Southern Africa and in the adjudication of the tenders for one of them.

Section Engineer / Section Manager / Technical Manager, Department for Water Affairs, Construction Division, Vanderkloof Dam on Orange River

START Date
END Date

1973 - mid 1974:  Section Engineer for "Services": Personel access to all areas of dam wall, precast yard installation and operation (production of 250 m3 of conrete in precast units per month), steel cutting and bending facility, carpenter workshop, provision of services to works areas (washing water, curing

Site Agent, LTA Civil Engineering (South) (Pty) Ltd, Water Treatment Plant for Mossel Bay at Kleinbrak River

START Date
END Date

Construction of a Water Treatment Plant for Mossel Bay at Kleinbrak River and assisting another site team under an inexperienced Site Agent at Natures Valley with technical advice on a bridge construction project.

Contracts Manager / Closing down Manager, LTA Earthworks: Vrey & Maine (Pty) Ltd, Various Contracts

START Date
END Date

Finish all works, including maintenance after final account, prepare payment claims and final accounts, negotiations with Engineers and clients, collecting final payments. Contracts at Grabouw, Laingsburg, Cape St Francis and Kenton on Sea.

Construction Methods Analyst, JP KRIEL Project Services, Various

START Date

ndependent construction analyst for improvement of production by defining the most efficient work methods and the best order of works, application of the contract to ensure that a contractor is paid his full entitlement, contractual analysis in support of requests for extension of time, final account measurement and the development and negotiation of new rates for items not included in the tender documents.