Thameslink - London Bridge Station Redevelopment

Change Manager, Costain, Thameslink - London Bridge Station Redevelopment

START Date
END Date
  • Enforcement of the Network Rail project change management process which produces actual forecast cost (AFC) and actual forecast value (AFV) reports.
  • Review and approval of budget and cost movements between subcontractors, Network Rail and Costain, to ensure the transaction is auditable and contractually valid.
  • Implementation of correct use of the online change management tool (“Salesforce”) through training sessions and presentations to the project commercial team.

Assistant Planner or Planning Engineer, Costain, Thameslink - London Bridge Station Redevelopment

START Date
Experience Hours (Planning & Scheduling)
2000
Experience Hours (Cost Management)
500
Experience Hours (Forensic Analysis)
500

2013 – 2015 Current works – Costain - London Bridge Station Revelopment (as part of the Thames link programme worth £6.5 Billion):
I currently work for Costain at London Bridge Station Redevelopment, since working here I have experienced planning for civil works undertaken by Costain (otherwise known as self-delivery works) and Early works such as demolition, piling and drainage (which have been part self-delivery and part subcontracted).
I do both short term and long term planning.

Assistant Planner or Planning Engineer, Costain, Thameslink - London Bridge Station Redevelopment

START Date
Experience Hours (Planning & Scheduling)
2000
Experience Hours (Cost Management)
500
Experience Hours (Forensic Analysis)
500

2013 – 2015 Current works – Costain - London Bridge Station Revelopment (as part of the Thames link programme worth £6.5 Billion):
I currently work for Costain at London Bridge Station Redevelopment, since working here I have experienced planning for civil works undertaken by Costain (otherwise known as self-delivery works) and Early works such as demolition, piling and drainage (which have been part self-delivery and part subcontracted).
I do both short term and long term planning.

Principle Planner, Network Rail Ltd, Thameslink - London Bridge Station Redevelopment

START Date

Current role: 

Principle Project Planner - Thameslink - Network Rail

Key Output 1 - Railway Systems Blockade and Possession Planner. 

                   - Programme Planner

Key Output 2 (London Bridge Station Redevelopment)

                  - Fitout and Finish Planner (Main concourse & Back of house plant rooms)