Planning Coordinator, Parsons International Limited, Tengizchevroil, Second Generation Project
START Date
END Date
- To coordinate eight area planners and seven planning technicians ensuring that all correct project procedures were being maintained for this $2.3 billion project.
- To ensure that all project progress databases are correctly being updated and developed as the project demands.
- To liaise with all sub-contractors and area planners to ensure that correct progress and any assistance required in specific project areas is provided.
- Programme reschedule for “off sites” section of the project comprising of six sub projects with 2.4 million man-hours due to engineering over