Puma Klabin Project

Planner Project, SGS, Puma Klabin Project

START Date
END Date
Experience Hours (Planning & Scheduling)
1550
Experience Hours (Cost Management)
1550
Experience Hours (Forensic Analysis)
1550

Notifying the commissioning team the released engines for testing of Cables Continuity (Electric room x field); Physical infrastructure, Advancement Report, cable launch; Connecting cables in motors and instruments, Assembling Electrical equipments and instruments;Critical Path Analysis – Interface between the phases of Civil construction, Mechanical, electrical, instrumentation, automation and commissioning;Issuance and Upload Check-List electrical assembly of motors, panels and Instruments in the system Pims completion Valpro;Issuance of Labor histogram.