Senior Planner, DPS Limited, Nuclear new build

START Date
Experience Hours (Planning & Scheduling)
2150
Experience Hours (Cost Management)
300
Experience Hours (Forensic Analysis)
0
  • Leading project scoping and planning activities within the Licensing, Management System, Power Station Design and Business Development programmes
  • Interfacing with the EPC contract partners; including setting schedule expectations, reviewing contractor schedules and integration of contractor schedules into the client's wider programme
  • Introducing best practice methodology in scope definition and schedule development including standardisation of Work Breakdown Structures (WBS), WBS dictionaries and Basis of Schedule documents
  • Conducting Schedule Integration Worksh