Construction Manager, Harry Peers Steelwork, Longannet Power Station - FGD
Construction Manager for Harry Peers Steelwork on FGD Project at Longannet Power Station, Scotland.
Construction Manager for Harry Peers Steelwork on FGD Project at Longannet Power Station, Scotland.
I spent four months assisting on a claim for the project. This included the production of a P3 programme which visualised the historical data collected in the analysis of many drawings, documents and the contract. Utilising my extensive knowledge of Earned Value allowed me to clearly analyse data and S-curve’s, ensuring I was fully prepared for discussions with the project manager and confident presenting to the client. I also often progressed the program actuals using P5 and updated the expended man hours on a weekly basis.
Managing the production of a Level 5 commissioning programme to be integrated into the master delivery programmes, working as Project Controller at the Longannet Power Station, Scotland. Constant communication with the Commissioning Manager as well as daily meetings with the project team allow me to be kept up to date of current progress and able drive the planning teams within the joint venture to implement the solution both accurately and correctly. I also frequently interface with the client in a formal setting.