London Underground PPP

Track Enabling Works Planner, Balfour Beatty Major Civil Engineering & Metronet, London Underground PPP

START Date
END Date

 

01/2007 – 10/2008           Balfour Beatty Civil Engineering/Metronet         Track Enabling Works Planner

 

The job involved using the Track Renewal Programme for the London Underground to make changes to the Track Enabling Works schedule. Failure to deliver on time cost millions of pounds making our working environment fast paced and high pressured.

 

Key Responsibilities & Achievements:

PROJECT ENGINEER, EDF Energy, London Underground PPP

START Date
END Date

 

·            Manage Planners, Site Engineers, Administrators and site operatives, providing support and coaching as required.

·            Responsibility  for commercial aspects of work and management of all Site Information Requests (SIRs)

·     &nbs

Lead Planning Engineer, Metronet Alliance, London Underground PPP

START Date
END Date

Lead Planner on Stations East Projects for Metronet Alliance

 

  • Reported programme status for stations in the East of London to the Senior Management team outlining key issues, maintaining a strict focus on delivery.
  • Managed a team of sixteen planners, meeting periodically to get an understanding of the key issues and mitigation measures taking place on the projects.
  • Working with QS fully cost loaded programmes to activity level to ensure accur